Wednesday 27 November 2013

Rough in and plastering Starts - 06 November 2013

Well the PD team power on. On the 6th November we had the alarm system roughed in with eaves being installed and the fridge tap (a late addition) also put in. A note for this considering a new fridge, it is hard to buy a family fridge without a need for a water connection, so well worth doing it when you get the chance at tender stage.

On the 7th the plasterers arrived and we thought they might take 2 weeks, but they only took 4 days !!
Wow it looks great too.



The upstairs family room...


The kitchen and butlers pantry...


Our fireplace... now behind plaster...


While the plaster was going on our 2nd story bricks got cleaned on the same day.. the eaves were painted on the 11th of November and they worked hard to remove the scaffolding which revealed the house ... Finally !!




The front facade and colour comes to life....